Archive

Posts Tagged ‘power lines’

Slovakia : power lines, electricity distribution

April 22nd, 2009

Project name Extension of Bošáca Substation - Transformer T402
Country Slovak Republic
Business sector Nuclear safety
Project ID 9639
Funding source BIDSF
Type of contract Supply and Installation
Type of notice Invitation for Tenders
Issue date 20 Apr 2009
Closing date 24 Jun 2009 at 12:00, Slovakian time
INVITATION FOR TENDERS

Slovenská elektrizacná prenosová sústava, a.s. (SEPS, a.s.), hereinafter referred to as the Employer, has received a grant from the Bohunice International Decommissioning Support Fund (BIDSF), administered by the European Bank for Reconstruction and Development (EBRD) towards the cost of the supply of electrical and instrumentation and control equipment and related works and services as required for the reconstruction measures of the Bošáca Substation to adapt the substation to the conditions of the grid after the final shutdown of Bohunice Nuclear Power Plant, Units 1 and 2 (Bohunice V1 NPP).
The Employer now invites sealed tenders from Suppliers / Contractors for the following contract to be funded from part of the proceeds of the grant:
Contract for the design, manufacture, pre-assembly and acceptance testing in the manufacturers’ workshop as well as the transportation to site, unloading, temporary storage, erection, interface co-ordination, adjusting, setting, identification, commissioning and acceptance testing, trial operation and making good all defects during the defects notification
period all required electro-mechanical systems for the Bošáca Substation mainly consisting
of:
• Supply and installation of 1 (one) new 400 kV bay including extension of double busbar system and transfer-bus system; instrument transformers will be of the combi-type (VT-CT), SF6 insulated.
• Supply and installation of 1 (one) new 400/110/10.5 kV autotransformer, 350 MVA, including heat-exchange system. Transformer foundation with oil pit for 20% of total transformer’s oil capacity including connection to oil storage tank. A sufficient water-oil separator is existing.
• Supply and installation of 1 (one) reactor for compensation of capacitive load of the overhead transmission line, air insulated, directly connected to the 10.5 kV winding (without circuit breaker or load break switch).
• New 400/230 V AC and 220 V DC distribution switchgear.
• Supply and installation of a local protection and control system; voltage regulator and paralleling device is required.
• Re-programming of the digital substation control-system.

Procurement will be carried out in accordance with EBRD Procurement Policies and Rules with the exception of country eligibiltity restrictions definded within the BIDSF. (The eligible countries as at December 2008 are: the European Union member states, Switzerland and the EBRD’s countries of operations). The proceeds of the BIDSF’s grant will not be used for
the purpose of any payment to persons or entities, or for any import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations.
The Tender Documents may be obtained from the address below upon payment of a nonrefundable fee of EUR 140.00 (one hundred fourty), to the following account:
Beneficiary: Slovenská Elektrizacná Prenosová Sústava, a.s.
Account Number: 2620191900/1100
IBAN: SK30 1100 0000 0026 2019 1900
BIC (SWIFT): TATRSKBX
Bank: TATRA BANKA, a.s.
Upon request, the documents will be promptly dispatched by courier at the Tenderer’s expense, but no liability can be accepted for loss or late delivery.
All Tenders must be accompanied by a Tender Security of EUR 120,000.00 (one hundred twenty thousand), and must be delivered to the address below on or before - 12:00 h
Slovakia time, on 24 June 2009, at which time they will be opened in the presence of the Tenderer’s representatives who wish to attend.
A pre-tender meeting with site visit will be carried out to answer any questions on the Tender Documents and to enable the Tenderer’s to familiarize with the local conditions at the site.
The meeting including the site visit escorted by the Employer / Engineer will be held on 12 May 2009, starting at 8:00 h Slovakia time at:
Slovenská Elektrizacná Prenosová Sústava, a.s.(SEPS, a.s.)
Mlynské nivy 59/A
824 84 Bratislava
Slovak Republic
Prospective Tenderers may obtain further information from, and inspect and acquire thetender documents at, the following office:
Mr. Juraj Dosek
Head of PMU
Slovenská Elektrizacná Prenosová Sústava, a.s. (SEPS, a.s.)
Mlynské nivy 59/A
824 84 Bratislava
Slovak Republic
Fax: + 421-2-50692319
Email: Dosek_Juraj@sepsas.sk

admin Projects, Tenders , , ,

Turkey : Electricity Distribution

April 16th, 2009

WORLD BANK’S LOAN OF $600 MILLION FOR RES PROJECTS WILL BE SUBMITTED TO EXECUTIVE BOARD FOR APPROVAL
 
World Bank’s Loan of $600 Million for RES Projects will be Submitted to Executive Board for Approval

Negotiations held for the $600 million loan in Ankara in March in connection with the Renewable Energy Projects have resulted positively. Approval will be likely obtained from the World Bank Administration within this month and commencement of spending the loan is planned in May.

Negotiations held in Ankara in March resulted positively in connection with the World Bank’s loan package of $600 million to be spent by private sector for Renewable Energy Resource (RES) Projects, which have been prioritized by the Government.

Agreement was reached in the negotiations held on 30-31 March 2009 for the loan in question between the World Bank officials and Treasury Undersecretariat, Ministry of Energy and Natural Resources (MENR), Energy Market Regulatory Authority (EMRA) and Turkish Electricity Transmission Corp. (TEIAS).

As might be recalled, we earlier informed you that in case negotiations towards the $600 million RES loan concluded positively, a proposal for this loan would be forwarded to the World Bank Administration for approval.

Approval is expected to be obtained by end-April

Sources close to the subject have noted that the World Bank decided to support Turkey’s initiatives towards renewable energy and her targets to this end and a positive report will be prepared to be submitted to the Executive Board of the World Bank. This loan package of $600 million is composed of $500 million World Bank loan and $100 million loan obtained from the Clean Technology Fund (CTF). Approval of the World Bank is expected to be issued within April. As known, Turkey which is a quite rich country in terms of variety of renewable energy resources and potential, has revised her projections and developed new targets.

In this second stage of loan slice of the Renewable Energy Project, financed by the World Bank earlier, apart from electricity generation, energy productivity projects will also be supported financially and technically; this will also cover financing of the manufacturing industry which achieves energy productivity and saving from the loan.

Using the loan may commence in May

In case the loan is approved by the World Bank, using the loan might start within May. Relevant sources contend that with the World Bank loan amounting to $600 million, RES power plants of the private sector to have a total of 2,000 MW installed power can be financed, and that in this process Turkish Industrial Development Bank (TSKB) and Turkish Development Bank (TKB) will be intermediary institutions.

More Info

Contacts — In Ankara: Tunya Celasin, (+90-312) 459-8300
Tcelasin@worldbank.org
In Washington: Miriam Van Dyck, (+1-202) 458-2931
Mvandyck@worldbank.or

admin New Plants, Projects , ,

India : power distrubution

March 24th, 2009

Uttar Haryana Bijli Vitran Nigam is to construct new 33 KV substations in Kurukshetra district of Haryana. The project will construct 13 substations along with 33 KV and 11KV lines. As of February 2009, KGL Systel has been awarded the contract for erection supply of equipment at a cost of Rs.300 million. The project is slated for completion within 12 months.

Tags:

admin New Plants, Projects ,